Vanguard Magazine

Vanguard AugSep 2017

Preserving capacity, General Tom Lawson, Chief of the Defence Staff, Keys to Canadian SAR

Issue link: http://vanguardcanada.uberflip.com/i/870590

Contents of this Issue

Navigation

Page 18 of 47

www.vanguardcanada.com AUGUST/SEPTEMBER 2017 19 INTERVIEW I you know exactly what you are buying. We get involved quite early on in projects when the requirements are not fully set. Be- cause of that, it is difficult to produce cost estimates when there is so much uncertainty. So, managing that uncertainty is what I would consider the biggest challenge with costing. To tie that into the surface combatant discussion, for example, Defence has not yet picked a design. Trying to cost the program is tough when at a granular level, you don't know exactly what you're buying. There are a bunch of designs out there, so we have to look at all of them and try to do our work based on examin- ing each. That makes it difficult. That is why you end up getting some pretty broad cost ranges because you just don't know what you are going to end up with until the competitive process deliv- ers the final design. At that point in time, we will be able to get more specific. Q: Talking about Canadian Surface Combatant, what are your findings on the costing for this program? When you did your costing, did you look at future years as well? What is it going to cost in say 5 years? The number that was announced as part of the DPR is a range of $56 to $60 billion in what we call budget-year dollars or inflated dollars. That is the value of the cheques that the Government will have to write to purchase the asset for the full project, but it does not include any maintenance, sustainment or life cycle support costs. When we do a costing, part of the process is creating something called a point estimate. A point estimate includes a set of assump- tions associated with a project, like a delivery schedule. Then after that, we do a risk and sensitivity assessment. As part of this assess- ment, we will, as an example, simulate a change in the delivery schedule to see what happens to the cost estimate if it takes an extra year or two years to deliver this project. Essentially, we cost the plan and then add to the cost estimate a risk premium that will account for all sorts of potential risks, schedule slippage, foreign currency fluctuation, general inflation in the economy, design changes, and so on. Q: Did you do a comparison of cost in building the ships in Canada and overseas? No, we did not do that. Q: What methods or tools were used in your costing for CSC? We used a multitude of methods. There are four basic methods of cost estimating. You can use parametric estimate; that's what the PBO did by using a commercial software and parameters. There is something called "analogy" which uses a comparison to a similar project. Another method is called "engineering build-up" which is basically a breakdown into component parts and the cost for each part is determined. The final method is expert opinion. For our cost estimate we used a combination of all of these. It's important to note that we use the method that has the best information available and gives the best result. Each one of those methods has its strengths and weaknesses. Whatever information you have available determines which method you can use. Q: For CSC, did you used all four methods? Yes, a combination of all four. In addition, to be compliant with Treasury Board policy around cost estimating, we had an inde- pendent estimate prepared on our behalf. Q: Can you share a little more about that? Was there a variance? There is always going to be a variance between estimates, but the whole purpose for doing this independent cost estimate is to look at the result of an independent party doing the same thing to see if they get a similar result. In this case, the independent result was similar to both our result and that of the PBO. Q: According to the PBO's report, the current budget of $26.2 billion for CSC would only allow us to build six ships. What are your thoughts on that? Is that within your calculations as well? We tried to look at that a little bit as well, and we came up with a similar result. Q: Is there anything else you would like to add about costing for CSC? Yes, in preparing the cost estimate for CSC, we also used third party expert input and review. For example, if the contractor told us it is going to take so many labour hours to do a piece of work, we ask the third party to validate that estimate. So, it's not like we are just going along with what the contractor says. It is about seeking input from experts from around the world in shipbuilding to confirm that the contractor's estimate of level of effort is in fact a reasonable estimate. Again, this is all about understanding the risk in the cost estimate. We have an estimate, but have not yet picked a design, so there's no scenario where the cost estimate won't change a little bit. This is what we are trying to get people to understand: what we are deal- ing with is uncertainty and risk. We are trying to put a range around the cost estimate with the understanding that some of the underly- ing assumptions will change, and those changes will affect the cost estimate that we have currently. That is not necessarily a bad thing, but we should keep it in mind and be planning for it. Also, we should be looking at updating the cost on a cyclical basis because this is a very large and complex program. This will be the largest purchase the government of Canada has ever made in terms of military equipment. In the future, we don't want to be in the same situation as we were in 2008 when we never formally relooked at that number for almost a decade. Q: How oen should costing be relooked at? By policy, every time we go back to government for an approval, we update the costing. So, it depends on how the project is moving along the approval process for when we redo the costing. There is no fixed schedule – like once a year or once every 18 months. A relook at the costing also depends on when new information is available. Q: Thanks for sharing your insight into costing for CSC. You're welcome. Anytime.

Articles in this issue

Links on this page

view archives of Vanguard Magazine - Vanguard AugSep 2017