THE DASHBOARD
www.vanguardcanada.com AUGUST/SEPTEMBER 2017 25
JUNE 2016
Keel-laying ceremony for
the first AOPS, the future
HMCS Harry DeWolf.
AUGUST 26, 2016
Steel cutting begins
for the second AOPS,
the future HMCS
Margaret Brooke.
OCTOBER 27, 2016
Competitive process
launched to select
design of Canadian
Surface Combatant.
MAY 2017
Keel-laying ceremony
for the second AOPS,
the future HMCS
Margaret Brooke.
JULY 2017
Centre and stern
mega-blocks of the
future HMCS Harry
DeWolf moved from
Halifax Shipyard's
indoor shipbuilding
facility outside to
land level.
AS OF JULY 2017
AOPS 1 –The future HMCS
Harry DeWolf
· All 64 units have been
constructed or are in
various stages of
construction
· 60 per cent complete
AS OF JULY 2017
AOPS 2 – The future
HMCS Margaret Brooke
· 22 of 64 units in various
stages of construction
· 15 per cent complete
· Significant production
eciencies are being
realized compared to
the first AOPS